Coastal GasLink has been issued stop work orders on a stretch of pipeline construction for the second time in just over a week, the latest in a pattern of environmental violations for polluting sensitive waterways. The pipeline project crosses about 625 lakes, rivers, creeks, wetlands, and streams in northern B.C. On Tuesday, the BC Environmental Assessment Office Compliance and Enforcement Branch said it had issued four stop work orders to Coastal GasLink late last week because erosion and sediment were negatively impacting the upper Anzac River watershed, about 130 kilometres northeast of Prince George.
Pipeline company ordered to stop work near Prince George for polluting fish-bearing stream
The B.C. government has ordered Coastal GasLink to stop work on a section of pipeline near Prince George after officials found sediment-laden water being "pumped into an area that ran into tributaries of the Anzac River." In an email to CBC News, B.C.'s Environmental Assessment Office said there were "negative impacts" to a fish-bearing stream, a matter it takes "very seriously."
Coastal GasLink reports 2 spills while tunnelling under Morice River in northern B.C.
The B.C. Energy Regulator (BCER) is investigating after Coastal GasLink (CGL) reported two spills of clay lubricant while it was tunnelling under the Morice River to build a natural gas pipeline through northern British Columbia. The area around the Morice River has for years been the site of conflict between Wet'suwet'en hereditary chiefs and supporters, and CGL, its workers and the RCMP.
What is the hose along Highway 35?
Drivers had something new to observe on Highway 35, this past week, at the point informally known as Hopper’s Hill, featuring the Omineca Ski Club at the base. A long hose was unmistakably strung out along the long incline. It is at least six kilometres in length. It was a topic of watercooler chatter since it appeared. It was natural to surmise that it had something to do with the industrial activity not too far beyond the apex of the hill. That’s where the installation work is being done to build the natural gas pipeline through the area.
Coastal GasLink warned more than 50 times over environmental violations during pipeline construction
Coastal GasLink has now been warned more than 50 times about environmental violations during construction of its natural gas pipeline across northern British Columbia, according to the province. In an email to CBC News, the Ministry of Environment and Climate Change said it had issued a total of 51 warnings, 16 orders, and levied two fines — penalties of more than $240,000 "for repeated non-compliance" — since construction on the pipeline started in 2019.
Coastal GasLink Faces More Water Pollution Concerns
Coastal GasLink is facing more criticism over water-quality concerns as a result of construction on its 670-kilometre pipeline through northern B.C., this time in the western portion of the route near Kitimat. On Feb. 19, the company received an order from B.C.’s Environmental Assessment Office for allowing sediment to flow into a watercourse where its pipeline right-of-way crosses the South Hirsch Forest Service Road, just east of Kitimat. The order requiring the company to prevent sediment-laden water from entering watercourse comes days after the company was fined $72,500 for similar violations that have repeatedly been identified along the pipeline route.
Wet'suwet'en members prepare for winter, plan to stay until Coastal GasLink work halted permanently
It's been more than 40 days since Wet'suwet'en members and supporters occupied a Coastal GasLink work site near the Wedzin Kwa (Morice River) — and despite multiple arrests, they say they're determined to stay put until Coastal GasLink permanently halts work on their territory. "It's our sacred headwaters, our clean drinking water, and our salmon spawning river," said Sleydo', referring to the Wedzin Kwa. Sleydo', whose English name is Molly Wickham, is the spokesperson for the Gidimt'en Checkpoint, which controls access to the part of the Wet'suwet'en territory on which the drill site is located.