Lorne Street Storm Water Mitigation Project Phase III Update July 5

Lorne Street Storm Water Mitigation Project Phase III Update July 5

Installation of the water control structure at the Pickard Quarry and final site work is complete. Originally scheduled to take until August to construct, Beale & Inch completed the work last week. Once again, we appreciate the cooperation from Quarry Lane residents during construction.