The key contractor on a billion-dollar wastewater plant in North Vancouver is firing back at Metro Vancouver after the regional district said it is scrapping the project’s contract. The district recently said contractor Acciona Canada appeared to have “abandoned” the project. On Friday, it said it had “no choice” but to terminate the deal, accusing contractor Acciona of having “failed to meet its contractual obligations, which include delivering the project on time and within budget, as required under the initial fixed-cost design-build-finance model.” On Sunday, Acciona responded, claiming Metro Vancouver owed it millions of dollars.
Metro Vancouver Regional District cancels wastewater treatment plant deal after delays
The contract to build the new wastewater treatment plant in North Vancouver, B.C., will be terminated, according to the regional district in charge of the project, but the building company says it's still working on it. The head of the Metro Vancouver Regional District says it lost confidence in Acciona, the contractor company, after long construction delays and a rising price tag. Jerry Dobrovolny, chief administrative officer for the regional district, says the cost has risen double the original estimate of $500 million.
Work stops on $1B North Shore water treatment plant amid layoffs by contractor
Work has ground to a halt on construction of a $1-billion wastewater treatment plant in North Vancouver, B.C., after mass layoffs by the contractor. Metro Vancouver commissioner Jerry Dobrovolny said he learned Wednesday that Acciona Wastewater Solutions LP has "significantly reduced" the number of people working on the North Shore Wastewater Treatment Plant.